Complete Timeline
| Purchase Deadline | 28 November 2025 | Final deadline to purchase manufacturing slots |
| Design Submission | 3 December 2025 | Final deadline to submit GDS files for fabrication |
| Tape-out to GlobalFoundries | 5 December 2025 | GDS files delivered to GlobalFoundries for fabrication |
| Fabrication Complete | February 2026 | Wafers returned from GlobalFoundries fabrication |
| Delivery to Customers | 15 March 2026 | Finished dies shipped to customers worldwide |
Technical Specifications
GF180MCU Process Technology Details
Die Dimensions
19.67 mm²
3.88mm × 5.07mm
Metal Layers
5 Layers
Full routing capability
Quantity
1,000 dies
Per manufacturing slot
Capacitors
MIM & PIP
Metal-insulator-metal available
Resistors
Poly & High-Res
Multiple resistor types